奮戰一季度、加力開新局!
導語:
3月10日,廣西路建(jian)工程集團有(you)限公(gong)司賀州至巴馬(ma)高(gao)速公(gong)路(都安至巴馬(ma)段)三分部常谷1號高(gao)架大橋全幅貫通(tong),同時也標(biao)志著該項目(mu)主線實現全幅貫通(tong)。
廣西(xi)路(lu)(lu)建集團參建的都巴(ba)高速公路(lu)(lu)一(yi)(yi)分部、二分部、三分部圍繞(rao)項(xiang)目通車(che)節點目標,干字當先、主動出(chu)擊,迅速掀(xian)起(qi)一(yi)(yi)季(ji)度施工大干熱潮(chao)。
都巴一分部
都巴一分部(bu)24小時不間斷進(jin)行(xing)瀝青攤鋪,截至(zhi)3月11日(ri),已完(wan)成(cheng)一季(ji)度計(ji)劃(hua)產值的70%。其中,墊(dian)層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率62.1%(含(han)大(da)化連(lian)(lian)線(xian)),底基(ji)層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率75.2%(含(han)大(da)化連(lian)(lian)線(xian)),基(ji)層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率70.9%(含(han)大(da)化連(lian)(lian)線(xian)),功(gong)能層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率76.5%,下面層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率84.8%,中面層(ceng)(ceng)(ceng)(ceng)(ceng)完(wan)成(cheng)率111.1%。
都(dou)巴一分部都(dou)安南互通 覃輝銅/攝
項目控制(zhi)性重點工(gong)程大(da)化連接線是(shi)都(dou)巴高速的進城(cheng)大(da)道,2020年12月(yue)底(di)由二級(ji)路提升為一級(ji)路。
大(da)化(hua)連接線預計3月(yue)底完成L1K1+738—L1K2+474級(ji)配碎石墊(dian)層(ceng)攤(tan)鋪,屆時將進(jin)入路面施工大(da)干階段。
都(dou)巴一(yi)分部夜間瀝青攤鋪施工 覃輝銅/攝(she)
弄莫隧(sui)(sui)道(dao)是(shi)都巴一(yi)分部(bu)最長的隧(sui)(sui)道(dao)。由于溶洞發育復雜(za),圍巖穩定(ding)性(xing)較差,是(shi)目(mu)(mu)前(qian)項目(mu)(mu)施工(gong)工(gong)作的“重中之重”。經科學組織(zhi)、精心籌劃,項目(mu)(mu)計(ji)劃于近日進行弄莫隧(sui)(sui)道(dao)右(you)洞溶洞段隧(sui)(sui)底預應力梁砼澆筑,比原計(ji)劃節點提前(qian)近半個月,為順利實現(xian)通車目(mu)(mu)標奠定(ding)良(liang)好基礎。
都巴二分部
都巴二分部是都巴高速全線進度最快的項目,截至3月10日,已完成一季度計劃產值的68.8%。目前,項目主線瀝青中面層、下面層已全部完成,正在進行剩余附屬工程和臨時用地復墾工作。
都巴二(er)分部巴獨(du)隧道出口航拍圖 張(zhang)鈺婷/攝
項目(mu)新進(jin)場8臺鉤機、1臺裝載機,復墾(ken)工作(zuo)多點(dian)開花(hua),現(xian)已(yi)完成約110畝臨時用地(di)(di)的(de)砼硬化破除、場地(di)(di)平整及表(biao)土覆蓋等工作(zuo),復墾(ken)完成率(lv)超(chao)60%。下一步(bu),項目(mu)將積(ji)極與各縣政府(fu)、村委多方(fang)協調,按要求辦好臨時用地(di)(di)移交手續,盡快將土地(di)(di)交付村民使用。
綠化種植(zhi)土回填 梁偉鋒/攝
都巴三分部
都(dou)巴三分部主(zhu)線全長10.4公里,主(zhu)線橋梁(liang)工(gong)(gong)程(cheng)已全部進(jin)入橋面(mian)系施工(gong)(gong)階段,房建工(gong)(gong)程(cheng)完成86.2%,交安工(gong)(gong)程(cheng)及(ji)綠化工(gong)(gong)程(cheng)、瀝青下面(mian)層(ceng)(ceng)和(he)中面(mian)層(ceng)(ceng)施工(gong)(gong)正(zheng)穩(wen)步推(tui)進(jin)。為拓寬瀝青路面(mian)攤(tan)(tan)鋪(pu)(pu)施工(gong)(gong)作業面(mian),項目引進(jin)了(le)一(yi)套水穩(wen)攪拌(ban)站(zhan)、一(yi)套瀝青攪拌(ban)站(zhan)及(ji)配套攤(tan)(tan)鋪(pu)(pu)碾(nian)壓機、攤(tan)(tan)鋪(pu)(pu)機,有效提(ti)高了(le)瀝青路面(mian)攤(tan)(tan)鋪(pu)(pu)質量(liang)和(he)攤(tan)(tan)鋪(pu)(pu)速度(du)。
都巴(ba)三分部路基邊坡防護順直美觀 陽馥蔓/攝
項(xiang)目嚴格控(kong)制施(shi)工(gong)(gong)(gong)方案(an)、材料、工(gong)(gong)(gong)藝、設(she)備,全力打造品質工(gong)(gong)(gong)程——使用不銹鋼模板(ban),橋(qiao)梁(liang)墩柱線(xian)型更(geng)美觀(guan);對滾(gun)焊(han)機設(she)備進行微改(gai)造,解決滾(gun)焊(han)機上鋼筋(jin)(jin)(jin)籠主(zhu)筋(jin)(jin)(jin)微彎(wan)施(shi)工(gong)(gong)(gong)的難題(ti);采用高速液壓強夯機,提高回填土壓實度;應用預制梁(liang)波(bo)紋(wen)管(guan)定位箍筋(jin)(jin)(jin)加工(gong)(gong)(gong)胎架微改(gai)創技術,使鋼筋(jin)(jin)(jin)骨架線(xian)型美觀(guan)、各筋(jin)(jin)(jin)間距均勻標準,提高了工(gong)(gong)(gong)程整(zheng)體(ti)質量(liang)。
都巴三分部(bu)引入(ru)新設備(bei)進行瀝青攤鋪 陽馥蔓/攝(she)
在(zai)全(quan)(quan)(quan)力(li)沖刺階段,都巴(ba)三分(fen)部始終(zhong)將安(an)全(quan)(quan)(quan)生(sheng)產擺(bai)在(zai)第(di)一位,強(qiang)化(hua)施工(gong)現場安(an)全(quan)(quan)(quan)標準化(hua)管理和員工(gong)的安(an)全(quan)(quan)(quan)教育培訓,加(jia)強(qiang)日常安(an)全(quan)(quan)(quan)巡(xun)查力(li)度(du),組織開展安(an)全(quan)(quan)(quan)專項(xiang)檢查,有效防(fang)范生(sheng)產安(an)全(quan)(quan)(quan)事故(gu)發生(sheng)。
決戰的號角已吹響。路建(jian)(jian)集團參(can)建(jian)(jian)人(ren)員正晝夜(ye)兼程,豪情滿懷、勇往(wang)直前,向著最終勝利奮(fen)力沖刺!