桂林(lin)繞城(cheng)改(gai)造工(gong)程項(xiang)目右(you)幅(fu)中下(xia)面層瀝青全(quan)線(xian)竣工(gong)
9月18日上午10時,桂林繞城改(gai)造工程項(xiang)目(mu)(mu)瀝青施工前線又傳(chuan)來(lai)捷報:項(xiang)目(mu)(mu)右幅中(zhong)下面層瀝青施工全(quan)線竣工,這標志著項(xiang)目(mu)(mu)向通(tong)車(che)目(mu)(mu)標又邁(mai)進(jin)了一步(bu)。
中秋(qiu)節期間(jian),項目全(quan)體員(yuan)工(gong)(gong)(gong)放棄(qi)休息時間(jian)集中人力物力突(tu)擊右幅(fu)(fu)剩余的中下面(mian)(mian)層瀝青施工(gong)(gong)(gong),并(bing)將(jiang)項目施工(gong)(gong)(gong)難度最高、交通管制(zhi)壓力最大的桂(gui)(gui)林(lin)北粟家互通全(quan)部搶(qiang)工(gong)(gong)(gong)完畢(bi)。截(jie)止9月18日,桂(gui)(gui)林(lin)繞(rao)城改造(zao)工(gong)(gong)(gong)程項目中下面(mian)(mian)層已(yi)完成(cheng)(cheng)46KM(單幅(fu)(fu))、剩余左幅(fu)(fu)桂(gui)(gui)林(lin)北粟家互通1KM,完成(cheng)(cheng)率達98%;上(shang)面(mian)(mian)層已(yi)完成(cheng)(cheng)35KM,完成(cheng)(cheng)率達74%,剩余12KM。接下來,項目將(jiang)繼續集中人力物力對右幅(fu)(fu)瀝青上(shang)面(mian)(mian)層發起(qi)最后沖刺施工(gong)(gong)(gong),并(bing)加(jia)大監(jian)督管理力度,加(jia)強(qiang)對過往車流的引導,爭(zheng)取盡(jin)快將(jiang)右幅(fu)(fu)全(quan)線瀝青施工(gong)(gong)(gong)搶(qiang)工(gong)(gong)(gong)完畢(bi),為9月底竣工(gong)(gong)(gong)贏(ying)得寶(bao)貴時間(jian)。