馬(ma)平高(gao)速(su)路上新裝
--馬平2標三分(fen)部(bu)開展交通標線工程試驗段施工
近日,馬平路三分部開展交通標(biao)線工程試驗(yan)段施工,該試驗(yan)段位于K407+000~K410+000處右(you)幅(fu),全(quan)長3公里。交通標(biao)線工程的施工對馬平路10月底主體(ti)工程全(quan)面竣工跨出了(le)關(guan)鍵性的一步。
此次標線主(zhu)要有(you)主(zhu)線(xian)車道邊緣線(xian)、車道分界線(xian)、車距確(que)認(ren)標線(xian)等均采用具有耐磨性(xing)強、反(fan)光性(xing)好和(he)美觀鮮艷等特點的(de)白色(se)熱熔反(fan)光涂料;為(wei)了控制(zhi)標(biao)線工(gong)(gong)程(cheng)質量(liang),三分部精心編制(zhi)科學、合理(li)的實施(shi)(shi)性施(shi)(shi)工(gong)(gong)組(zu)織設計,以其作為(wei)施(shi)(shi)工(gong)(gong)指導,并嚴(yan)格按照施(shi)(shi)工(gong)(gong)圖紙(zhi)以及(ji)施(shi)(shi)工(gong)(gong)規范要(yao)求加快(kuai)工(gong)(gong)程(cheng)進度、確保工(gong)(gong)程(cheng)建立(li)在技術(shu)先進、措施(shi)(shi)有(you)效的基礎上,對行車安全、有序發揮著巨大的作(zuo)用。
截至目前,馬(ma)平2標(biao)三分部水穩層(ceng)(ceng)施工已接近尾聲(sheng),房建工程(cheng)(cheng)、瀝青面層(ceng)(ceng)施工亦(yi)(yi)穩步推進中(zhong)(zhong),其中(zhong)(zhong)瀝青下(xia)面層(ceng)(ceng)已完(wan)成(cheng)全幅30.4公里、瀝青中(zhong)(zhong)面層(ceng)(ceng)完(wan)成(cheng)全幅28.6公里、瀝青上面層(ceng)(ceng)全幅23.4公里;交安、綠化等(deng)附(fu)屬(shu)分項工程(cheng)(cheng)施工亦(yi)(yi)同步跟進。